The AER is responsible for monitoring compliance with the National Electricity Law and National Electricity Rules and with the National Gas Law and National Gas Rules. The AER may undertake detailed investigations of specific market events or unusual market behaviour.

Investigations reports are available to download.

Gas investigation reports



A report into the events of Sunday 10 August 2008, when there was a plant outage at the Moomba production facility. The production facility was not fully restored until Wednesday 13 August 2008.

Publication date: October 2008
Sector: Gas Rules
Related provisions: Clause 172 NGR 5.6(a) Bulletin Board procedures
Outcome: No further action


Electricity investigation reports



A report into compliance with the planning and consultation requirements for a new large transmission asset by TransGrid in the development of a line between Dumaresq and Lismore on the NSW far north coast.

Publication date: 10 September 2010
Sector: Electricity Rules
Related provisions: 5.6.6
Outcome: No further action, undertaking from TransGrid



A report into compliance with dispatch instructions by Babcock and Brown with respect to Playford power station in South Australia on 11 February 2009 and Braemar power station in Queensland on 17 March 2009.

Publication date: 10 December 2009
Sector: Electricity Rules
Related provisions: 4.9.8a
Outcome: Two infringement notices issued, undertakings from Babcock & Brown



A report into compliance of AGL Energy Limited (AGL) with the good faith rebidding provision of the Electricity Rules. The investigation focused on rebidding of Torrens Island Power Station (in South Australia) during February 2008.

Publication date: 12 May 2009
Sector: Electricity Rules
Related provisions: 3.8.22A
Outcome: No further action



A report into compliance with dispatch instructions by Braemar Power Project and the impacts of network congestion in Queensland on 4 November 2007.

Publication date: 28 January 2009
Sector: Electricity Rules
Related provisions: 4.9.8a, 4.9.8b
Outcome: Three infringement notices issued



A report into the derating of the Heywood interconnector in November–December 2007.

Publication date: 23 December 2008
Sector: Electricity Rules
Related provisions: 5.6.6, 5.6.2, 5.6.2A, 5.2.3(d), 9.28.3
Outcome: Undertaking from ElectraNet



A report into the events of 16 January, when bushfires caused the main transmission links into Victoria to fail. The transmission failure interrupted around a quarter of all Victorian customers' electricity supplies.


Publication date: 11 September 2007
Sector: Electricity Rules
Related provisions: 4.2.3f, 3.9.2, 3.9.3
Outcome: Proposed rule changes, undertaking from NEMMCO, 3 infringement notices, 4 technical compliance audits



An infringement notice was served on AGL Hydro Partnership over its use of the inflexibility and rebidding provisions of the National Electricity Rules with respect to its MCKAY1 generating unit on 22 March 2006.

Publication date: 31 August 2006
Sector: Electricity Rules
Related provisions: 3.8.22
Outcome: One infringement notice issued



A report into the events of 31 October 2005 when the failure of a major transmission line in New South Wales caused significant disruption to the market.

Publication date: 12 October 2006
Sector: Electricity Rules
Related provisions: 4.9.8(a), 4.11.2, 3.1(a), 4.3.1, 4.2.4(a), 4.2.6, 4.2.2(a), 3.8.22, 3.8.1, 3.7A, 3.1.4
Outcome: Undertakings from NEMMCO, proposed rule change


Pre July 2005 NECA investigations—Electricity