Australian Energy Regulator
 
 
 
Contact us
About us
News & speeches
Publications
Careers
Glossary
 

Final decision (11 June 2010)

Access arrangement final decision–NSW gas distribution network

The AER has released its final decision on JGN’s access arrangement proposal for the period 1 July 2010 to 30 June 2015.

The final decision requires revisions to be made to JGN’s revised access arrangement proposal and access arrangement information. These revisions are incorporated into the AER’s access arrangement proposal and the access arrangement information, both of which form an annexure to the AER’s final decision.

The AER’s access arrangement proposal

The AER expects to make a decision on its access arrangement proposal and publish the approved access arrangement by the end of June 2010.

The AER’s access arrangement proposal and the access arrangement information are available below.

The final decision has been amended to consistently reference the increase in tariffs in the Overview section to 2010–11.
 

Printer friendly
Notify me...
  • Email me if this page and sub-pages are updated