Dispute resolution panel determinations - Gas

2016

Unexpected scheduling result - October 2016
Determination

Simply Energy, AETV, APA, Red Energy, Lumo, Dodo ("The Participants") and AEMO - Participant compensation fund claim 2016

Overview

Claim for compensation by The Participants following an unintended scheduling result which occurred on 1 October 2016. There was no dispute on the details (set out in the report attached) or the compensation amounts.

AEMO Declared Wholesale Gas Market - Compliance-Report-and-Investigation-into-USR-following-event-on-1-October-2016 ( PDF 781.25 KB )

Panel Gregory H Thorpe
Round table forum by zoom 17 February 2017
Wholesale energy market dispute resolution adviser (WEMDRA) Shirli Kirschner
Compensation amount $116 494.09 (inclusive of GST) (Breakdown included in Determination)
Dispute resolution panel costs

$4400 (inclusive of GST)

WEMDRA costs $4433 (inclusive of GST) and disbursements
Determination Determination USR 1 October 2016 ( PDF 238.4 KB )
Submissions

Joint submission AEMO and AETV et al (final with all joined parties) - 9 May 2017 ( DOCX 1.09 MB )
Adviser guideline and application for compensation for USR - 2011

Hydro application for compensation for a USR - 24 February 2017 ( PDF 234.25 KB )

 

2010

2010 - Simply Energy and AEMO - Participant compensation fund claim
Determination Simply Energy and AEMO - Participant compensation fund claim 2010

Overview
Claim for compensation by Simply Energy following an unintended scheduling result which occurred on 29 June 2010.
The unintended scheduling result is the subject of a Market report entitled "Unintended Scheduling Result Gas Day 29 June 2010".
Panel Peter R D Gray
Round table forum 17 February 2011
Dispute adviser Shirli Kirschner
DRP costs $3200 (inclusive of GST)
Adviser costs $1980 (inclusive of GST)
Determination IPower Determination - 24 February 2011 ( PDF 730.12 KB )
Submissions Supplementary Submission for USR Hearing - 17 February 2011 ( PDF 283.95 KB )
AEMO - Unintended Scheduling Result Gas Day - 29 June 2010 ( PDF 419.73 KB )
AEMO and Simply Energy Joint submission to the dispute resolution panel ( PDF 337.35 KB )

 

2010 - AGL Sales Pty Ltd and Origin Energy and AEMO - Participant compensation fund claim
Determination AGL Sales Pty Ltd and Origin Energy and AEMO - Participant compensation fund claim - 2010
Overview

Claim for compensation by AGL and Origin following an unintended scheduling result that occurred on 15 March 2010 as part of the operating schedules for that gas day for injection of natural gas at the Longford injection point of the Victorian Declared Transmission System. AEMO investigated and declared an unexpected scheduling result.

AGL and Origin were awarded compensation from the Participant Compensation Fund to be paid by 30 June 2010.

Panel Peter R D Gray
Dispute adviser Shirli Kirschner
DRP costs (including the Adviser costs, not including parties individual legal fees) TBA
Commencement Form 2 Adviser Notice - AGL ( PDF 448.95 KB )
Unintended Scheduling Result - Gas Day Report - 15 March 2010 ( PDF 2.2 MB )
Submission AEMO, AGL and Origin Joint submission to the Dispute Resolution Panel - 9 June 2010 ( PDF 4.63 MB )
Determination Determination of Peter R D Gray - 10 June 2010 ( PDF 19.77 KB )

2008

Determination AGL v VENCorp (pre 2009)
AGL v VENCorp
Overview

A dispute between AGL Sales Pty Ltd and VENCorp relating to the failure of the market clearing engine software to prorate the minimum daily quantity bids of AGL and other wholesale gas market participants for gas supplied from Longford on specified dates in 2007.

AGL was unsuccessful in its claim that this was a scheduling error under the Rule for which it was entitled to compensation from a participant compensation fund.

Panel Sir Anthony Mason AC KBE, Ron Merkel QC and Greg Thorpe
Dispute Adviser Shirli Kirschner
Date of Determination 19 June 2009
Determination Dispute resoultion panel - Decision - AGL v VENCorp - 19 June 2008 ( PDF 1.67 MB )