Overview

 

In accordance with the f-factor scheme Order 2016, distributors provided in September 2018 their respective fire start reports for 2017–18 in accordance with specified reporting templates. The Australian Energy Regulator (AER) requested Energy Safe Victoria (ESV) to validate the fire start reports.

In November 2018, ESV provided initial validation reports to the AER, who in turn requested submissions from the distributors regarding the ESV’s initial validation findings. Submissions were received from Powercor and AusNet Services.

In February 2019, ESV provided final validation reports for each distributor.

The distributors' 2017–18 fire start reports (including updated versions, if any) and ESV's validation reports (initial and final) are provided below.

 

 

Documents (20) Author