Overview

On 1 March 2022 Powercor submitted an application under clause 6.6.1 of the National Electricity Rules to the AER for a positive pass through of costs associated with a new regulatory obligation to replace or reinforce 34,650 wood poles between 1 January 2022 to 31 December 2026.