AusNet Services – Cost pass through - June 2021 storms natural disaster
On 16 March 2022, the AER released its determination on AusNet Services' cost pass through application.
Type
Cost pass throughs
Status
Open
ElectraNet - Cost pass through - 2022–23 Inertia network service
Type
Cost pass throughs
Status
Open
Central-West Orana - Renewable Energy Zone - Ring-fencing class waiver
A class waiver under the electricity distribution Ring-fencing Guideline enables DNSPs to potentially build and operate transmission infrastructure in a REZ.
Type
Ring-fencing
Status
Open
Powerlink Transmission - Determination 2027-2032
The AER will make a determination of the maximum amount of revenue that Powerlink can earn from customers over the period 1 July 2027 to 30 June 2032.
Type
Determinations
Status
Open
AusNet Services Transmission - Determination 2027-2032
The AER will make a determination of the maximum amount of revenue that AusNet Services can earn from customers over the period 1 April 2027 to 31 March 2032.
Type
Determinations
Status
Open
South Australia: December 2026 - February 2027
In its September 2023 update to the 2023 ESOO AEMO has forecast a 205 MW reliability gap in South Australia in 2026–27.