Evoenergy - Cost pass through - Ring-fencing 2018

Sector: 
Segment: 
Status: 
Commencement date: 
7 December 2018
Effective date: 
6 February 2019
Service provider/Asset: 

Overview

On 7 December 2018, Evoenergy submitted an application to the AER under clause 6.6.1 of the NER for a positive pass through of costs associated with Evoenergy's compliance with the AER's Electricity Distribution Ring-fencing Guideline.

On 6 February 2019, the AER determined that Evoenergy's application satisfied the definition of a service standard event and a positive change event under the National Electricity Rules. The AER approved a positive pass through amount of $2.05 million ($2018-19) to be recovered from network users in the regulatory years 2019-20 and 2020-21.