Allgas Energy - gas distribution network

APA Group 20%, Marubeni 40%, RREEF 40%
APT Allgas
Covered by regulation: 
Yes (Light)
State of the Energy Market 2014


On 22 July 2015, Allgas Energy's gas distribution network became subject to light regulation, following the NCC’s Final Determination on 28 April 2015. The AER is no longer responsible for approving access arrangements but the AER is available to arbitrate in case of a dispute.

On 2 March 2012, APT Allgas changed its name to Allgas Energy Pty Limited - all other details remain unchanged.

Current regulatory period: 1 July 2011 - 30 June 2016

Customer numbers Mains length (km) Asset base ($million)
84 400 2 900 442

The asset base is the initial capital base, adjusted for additions and deletions, at the beginning of the current access arrangement period.

Access arrangements pre-2011
Before coming under the regulation of the AER, gas distribution access arrangements for APT Allgas were approved by the Queensland Competition Authority (QCA).