Roma to Brisbane Pipeline - Cost pass through – carbon cost event 2014

On 14 February 2014, APT Petroleum Pipelines Limited, operator of the Roma to Brisbane Pipeline, applied to the AER for a negative cost pass through of $397,678.

This is for the difference between forecast and actual carbon-related charges it had incurred.

If approved, the pass through will take effect from 1 July 2014.

Sector: 
Segment: 
Issued date: 
19 February 2014
AER reference: 
AC 016/14