TasNetworks - Network support pass through 2023-24
AER’s has determined TasNetworks' 2023-24 positive network support cost pass through should be reflected in TasNetworks' maximum allowed revenue for 2025-26
Type
Cost pass throughs
Status
Current
Powerlink - Network support pass through 2023–24
AER’s has determined Powerlink's 2023-24 positive network support cost pass through should be reflected in Powerlink's maximum allowed revenue for 2025-26
Type
Cost pass throughs
Status
Current
ElectraNet - Network support pass through 2023–24
AER’s has determined ElectraNet's 2023-24 positive network support cost pass through should be reflected in ElectraNet's maximum allowed revenue for 2023-28
Type
Cost pass throughs
Status
Current
AusNet Services transmission cost pass through - 13 February 2024 storm
AusNet Services submitted a cost pass through application seeking to recover the costs it has incurred as a result of the 13 February 2024 storm in Victoria.
Type
Cost pass throughs
Status
Open
Amadeus Gas Pipeline - 2025–26 tariff variation notice
APA Group has proposed new network prices to apply to its Northern Territory gas pipeline for 2025–26.
Type
Tariff variations
Status
Open
Roma to Brisbane Pipeline - 2025–26 tariff variation notice
APA Group has proposed new network prices to apply to its Queensland gas pipeline (transmission) for 2025–26.
Type
Tariff variations
Status
Open
Kurri Kurri Lateral Pipeline classification decision
On 16 May 2025, we published the final decision for to classify the Kurri Kurri Lateral Pipeline (KKLP) classification.
Type
Determinations
Status
Current
Transgrid - Ring-fencing waiver - Telecommunications services - April 2025
On 17 April 2025, the AER granted Transgrid a waiver to provide telecommunication services
Type
Ring-fencing
Status
Current
AusNet Services – Cost Pass Through – Easement Land Tax 2025-26
The AER has approved AusNet Services' application for a positive pass through of easement land tax to be recovered in 2025-26.
Type
Cost pass throughs
Status
Current
APA Victorian Transmission System - 2025 tariff variation notice
APA Victorian Transmission System submitted to the AER an annual tariff variation notice for the period 1 January 2025 - 31 December 2025.
Type
Tariff variations
Status
Current
Main Central-West Orana Renewable Energy Zone network project (contestable)
Read our determination on the amounts to be paid to ACEREZ for the main Central-West Orana REZ network project.
Type
Determinations
Status
Current
TasNetworks North West Transmission Developments Stage 1 – Early Works Contingent Project
On 10 October 2024, TasNetworks submitted its contingent project application seeking to increase its revenue to fund early works on NWTD stage 1 early works.
Type
Contingent projects
Status
Open