Overview

On 19 September 2017, ElectraNet wrote to the AER requesting a determination on its 2016-17 network support pass through application. The AER assessed the application in accordance with clause 6A.7.2 of the NER.

On 1 December 2017, the AER approved the pass through amount without adjustment.