Overview
On 10 April 2018, the AER received an application from Power and Water requesting an extension of time to submit an application for the pass through of costs associated with Tropical Cyclone Marcus.
On 27 April 2018, the AER extended the time limit for Power and Water to submit the pass through application until 3 December 2018.
Key documents
Documents | Author |
---|---|
AER - Letter to Power and Water - Request for extension of time to submit a pass through application - 27 April 2018 ( PDF 30.16 KB ) | AER |
Power and Water - Letter to AER - Request for extension of time to submit pass through application - 10 April 2018 ( PDF 1.92 MB ) | Power and Water Corporation (PWC) |