Overview

On 15 March 2018, Evoenergy (ActewAGL) submitted to the AER an annual tariff variation notice for the ACT, Queanbeyan and Palerang gas distribution network. The tariff variation notice sought to increase 2018-19 network charges for ActewAGL's users from 1 July 2018.

On 27 April 2018, Evoenergy submitted a revised tariff model, correcting for a few minor errors.

On 30 April 2018, the AER approved the Evoenergy revised annual tariff variation proposal for the period 1 July 2018 to 30 June 2019. This was after assessing the revised tariff variation proposal as compliant with Evoenergy's 2016-21 access arrangement.