Decision
Back to topOn 12 December 2014, the AER made its determination on the 2015 AMI charges in accordance with the applicable Order in Council. The charges allow Jemena to recover only those portions of its actual 2013 costs that the AER has determined to be prudent and efficient. The charges will take effect from 1 January 2015 to 31 December 2015. The determination also includes manual meter charges which will apply from 1 April 2015 to 31 December 2015.
Documents (1) | Author |
---|---|
AER final decision – AMI 2015 revised charges – 12 December 2014 ( DOCX 214.07 KB | PDF 528.83 KB ) | AER |
Consultant reports
Back to topThe AER commissioned Energeia's report which it took into account when making its determination.
Documents (1) | Author |
---|---|
Energeia Pty Ltd - Review of expenditure excess applications - December 2014 ( PDF 4.89 MB ) | Energeia |