Application
Back to topOn 20 December 2018, we received an application from Endeavour Energy to apply the new DMIS.
On 9 January 2019, we received an application from Ausgrid to apply the new DMIS.
The NER requires that, prior to making a decision on these applications, we seek submissions from stakeholders on the proposals from the electricity distributors for the early implementation of the new DMIS.
Documents (2) | Author |
---|---|
Endeavour Energy - Request for early application of the revised DMIS - 20 December 2018 ( PDF 187.55 KB ) | Endeavour Energy |
Ausgrid - Request for early application of the revised DMIS - 8 January 2019 ( PDF 92.17 KB ) | Ausgrid |
Submissions - Endeavour Energy application
Back to top11 January 2019 to 13 February 2019
We invited energy consumers and other interested parties to make submissions on Endeavour Energy's application by 13 February 2019.
Documents (1) | Author |
---|---|
Total Environment Centre - Submission on early application of DMIS by Endeavour Energy and Ausgrid - 14 January 2019 ( PDF 37.61 KB ) | Total Environment Centre (TEC) |
Submissions - Ausgrid application
Back to top11 January 2019 to 13 February 2019
We invited energy consumers and other interested parties to make submissions on Ausgrid's application by 13 February 2019.
Documents (1) | Author |
---|---|
Total Environment Centre - Submission on early application of DMIS by Endeavour Energy and Ausgrid - 14 January 2019 ( PDF 37.61 KB ) | Total Environment Centre (TEC) |