The AER has made its final decision on Transgrid’s Enabling Central-West Orana Renewable Energy Zone network infrastructure project (the CWO Enabling Project) revenue determination for the 2026–31 regulatory control period.
As required under the NSW Electricity Infrastructure Investment Act 2020 (EII Act) and Electricity Infrastructure Investment Regulation 2021 (EII Regulation), our revenue determination has been made within 126 business days of receiving a compliant revenue proposal from Transgrid on 31 July 2025.
In line with the EII Act requirements, we will publish our revenue determination, including the amounts payable for the project, following notification from EnergyCo that financial close for the CWO Enabling Project has been achieved.