Our approval role

A cost pass through event is one that occurs beyond the reasonable control of a network business and has not been accounted for in its current 5-year revenue determination.

Examples can include new statutory obligations imposed on the business or extensive damage to infrastructure caused by a natural disaster.

They can occur at any time during a regulatory control period.

Under the National Electricity Rules, network business can submit a cost pass through application to the AER to recover its efficient costs incurred by the event.

We undertake a rigorous assessment of the application and make a cost-recovery determination based on the principle that consumers should pay no more than necessary for safe and reliable energy.

Historical cost pass through decisions are archived and are available by emailing AERinquiryataer [dot] gov [dot] au (aerinquiry[at]aer[dot]gov[dot]au).

Cost pass through decisions

Results

Endeavour Energy – Cost pass through application – EBM

Endeavour Energy submitted an application seeking to recover costs relating to the NSW Emergency Backstop Mechanism.
Type
Cost pass throughs
Sector
Electricity
Status
Current

Ausgrid – Cost pass through application – EBM

Ausgrid submitted an application seeking to recover costs relating to the NSW Emergency Backstop Mechanism Order.
Type
Cost pass throughs
Sector
Electricity
Status
Current

Essential Energy – Cost pass through application – EBM

Essential Energy submitted an application seeking to recover costs relating to the NSW Emergency Backstop Mechanism.
Type
Cost pass throughs
Sector
Electricity
Status
Current

ElectraNet cost pass through application – October 2024 Storm

ElectraNet submitted a cost pass through application to recover costs incurred due to the 17 October 2024 storm event in South Australia.
Type
Cost pass throughs
Sector
Electricity
Status
Current

Powerlink cost pass through application – SoCI Act reforms

On 30 September 2025, Powerlink submitted a cost pass through application seeking to recover the costs it had incurred as a result of the SoCI Act reforms.
Type
Cost pass throughs
Sector
Electricity
Status
Current

AusNet Services’ cost pass through application – January 2026 bushfires

AusNet submitted a cost pass through application to recover costs incurred due to the January 2026 bushfires in Victoria.
Type
Cost pass throughs
Sector
Electricity
Status
Current