Sector
Gas
Segment
Transmission
Region
Northern Territory
Status
Current
Categories
Category 2
Classes
Exempt
Notice status
Current notice
Effective date
Application date
Expiry date
Applicants
EII Pipelines (WPP) Pty Ltd / ACN 131 331 676

Wickham Point Pipeline and Weddell Lateral was originally granted a 5 year Category 2 non-scheme pipeline exemption under Part 23 on 3 January 2018. On 30 November 2022, this exemption was extended until 3 January 2028.

Gas pipeline regulation reforms to the National Gas Law and National Gas Rules were proclaimed in March 2023. Wickham Point Pipeline and Weddell Lateral's Category 2 exemption under Part 23 was taken to be a Category 2 exemption under Part 10 as it is a single user pipeline. 

Documents

AER letter to APA re pipeline exemptions dated 30 November 2022

Authors
AER
Content type
Document

AER Letter to EII re Exemption Application - Wickham Point Pipeline (including Weddell Lateral) - 3 January 2018

Authors
AER
Content type
Document

Wickham Point pipeline and Weddell Lateral Map

Authors
APA Group
Content type
Document