Overview

Application - Powerlink's proposal

On 17 March 2010, the AER received Powerlink’s application for a proposed early date of 14 July 2010 for implementation of the market impact component of the scheme. In accordance with Clause 11.32.3(f) of the NER, the AER has determined that the proposal is compliant with the submission guidelines in respect of the service target performance incentive scheme.

Powerlink - Letter to AER - Proposal for early application of the market impacts of transmission congestion measure - 17 March 2010

Authors
Powerlink Queensland
Content type
Document

Powerlink's proposed performance target data - 17 March 2010

Authors
Powerlink Queensland
Content type
Document

Stakeholder forum

On 30 March 2010, the AER published Powerlink’s proposal and invited written submissions from interested parties. Submissions closed on 21 April 2010. No submissions were received.