Energex's Legacy Meter Replacement Plan (LMRP) was submitted on 30 June 2025. It sets out the planned replacement of legacy meters in its network over the LMRP Period (1 December 2025 to 30 November 2030) and the processes used to develop this plan.
Under clause 11.177.4 of the National Electricity Rules, the AER is required to approve a Legacy Meter Replacement Plan that complies with the LMRP Requirements and publish the plan on the AER’s website within 10 business days of its approval.
Energex’s Legacy Meter Replacement Plan was approved on 27 August 2025.
Energex must, within 20 business days of the AER approving the plan, notify affected retailers and metering coordinators and provide them with a copy of the meter replacement schedules. By no later than 27 November 2025, Energex must also record the relevant details of the Legacy Meter Replacement Plan as set out in the Market Settlement and Transfer Solution Procedures.