Project timeline

Overview

Final decision

On 21 May 2026, we released our final decision on Evoenergy's access arrangement proposal for the 2026–31 period commencing 1 July 2026.

Our final decision is set out in the Overview and accompanying attachments. For issues that were settled at the draft decision stage or required only minor updates, our draft decision reasons form part of this final decision.

AER - Final decision - Evoenergy access arrangement 2026–31 - Overview - May 2025

Content type
Document

AER - Final decision - Evoenergy access arrangement 2026–31 - Attachment 1 - Capital base, Regulatory depreciation and Corporate income tax - May 2026

Authors
AER
Content type
Document

AER - Final decision - Evoenergy access arrangement 2026–31 - Appendix A - Regulatory depreciation - May 2026

Authors
AER
Content type
Document

AER - Final decision - Evoenergy access arrangement 2026–31 - Attachment 2- Capital expenditure - May 2026

Authors
AER
Content type
Document

AER - Final decision - Evoenergy access arrangement 2026–31 - Attachment 3 - Operating expenditure - May 2026

Authors
AER
Content type
Document

AER - Final decision - Evoenergy access arrangement 2026–31 - Attachment 5 - Reference services, tariffs and non-tariff components - May 2026

Authors
AER
Content type
Document

AER - Final decision - Evoenergy access arrangement 2026–31 - Attachment 6 - Capital expenditure sharing scheme - May 2026

Authors
AER
Content type
Document

AER - Final decision - Evoenergy access arrangement 2026–31 - Attachment 7 - Efficiency carryover mechanism - May 2026

Authors
AER
Content type
Document

Evoenergy-FINAL-Access arrangement 2026-31-CLEAN-May 2026

Authors
Evoenergy
Content type
Document

Evoenergy-FINAL-Access arrangement 2026-31-marked up-May 2026

Authors
Evoenergy
Content type
Document

Evoenergy-FINAL-Reference Service Agreement 2026-31-CLEAN-May2026

Authors
Evoenergy
Content type
Document

Evoenergy-FINAL-Reference Service Agreement 2026-31-marked up-May2026

Authors
Evoenergy
Content type
Document

Models

Our models relating to Evoenergy's final decision.

AER - Final decision - Evoenergy access arrangement 2026–31 - Capex model - May 2026

Authors
AER
Content type
Document

AER - Final decision - Evoenergy access arrangement 2026–31 - CESS model - May 2026

Authors
AER
Content type
Document

AER - Final decision - Evoenergy access arrangement 2026–31 - Opex model - May 2026

Authors
AER
Content type
Document

AER - Final decision - Evoenergy access arrangement 2026–31 - ECM model - May 2026

Authors
AER
Content type
Document

AER - Final decision - Evoenergy access arrangement 2026–31 - PTRM - Step 2 - May 2026

Authors
AER
Content type
Document

AER - Final decision - Evoenergy access arrangement 2026–31 - RFM - May 2026

Authors
AER
Content type
Document

AER - Final decision - Evoenergy access arrangement 2026–31 - Depreciation tracking module - May 2026

Authors
AER
Content type
Document

Consultant reports

We commissioned the following report, which we took into account when making our final decision for Evoenergy.

Deloitte Access Economics - Labour price growth forecasts - March 2026

Authors
Deloitte Access Economics (DAE)
Content type
Document