Application

On 30 June 2026, Endeavour Energy submitted a cost pass through application seeking to recover costs it expects to incur as a result of the varied licence conditions for the NSW Emergency Backstop Mechanism Order. 

Endeavour Energy is proposing to recover incremental revenue of approximately $16.9 million (real, $2024) in the last two years of the current regulatory period as follows:

  • $10.8 million (smoothed, $2024) in 2027-28
  • $6.2 million (smoothed, $2024) in 2028-29.

Submissions

Interested parties are invited to make a submission on Endeavour Energy's cost pass through application by 21 August 2026.

Documents

Endeavour Energy – NSW Emergency Backstop Mechanism – Cost pass through application – June 2026 – Public

Content type
Document

Endeavour Energy – Attachment 2 – AEMO letter confirming MSL response capabilities – January 2026 – Public

Content type
Document

Endeavour Energy – Attachment 3 – Ministerial notice of intent to vary licence conditions – December 2024 – Public

Content type
Document

Endeavour Energy – Attachment 4 – Licence conditions – June 2026 – Public

Content type
Document

Endeavour Energy – Attachment 5 – Ministerial notice of variation of licence conditions – December 2025 – Public

Content type
Document

Endeavour Energy – Attachment 6 – Endeavour Energy Letter request for extension of cost pass through lodgement date – February 2026 – Public

Content type
Document

Endeavour Energy – Attachment 7 – AER cost pass through lodgement date extension confirmation – March 2026 – Public

Content type
Document

Endeavour Energy – Attachment 9 – EBM PTRM – June 2026 – Public

Content type