On 23 September 2026, VicGrid and Transgrid, the joint proponents of VNI West, notified us that they consider there has been a material change in circumstances for the project under clause 5.16A of version 202 of the NER.
The proponents consider that the regulatory investment test for transmission (RIT-T) does not need to be reapplied because Option 5A, identified in the May 2023 Project Assessment Conclusions Report, remains the preferred option. Their view is informed by AEMO’s final 2026 Integrated System Plan and their own analysis, taking into account updated project scope, cost and timing estimates.
On 18 November 2026, we advised VicGrid and Transgrid that the circumstances requiring the RIT-T to be reapplied under clause 5.16A.4(n) of version 202 of the NER have not been shown to have arisen. We will therefore not make a determination under that clause at this stage.
We would normally assess compliance with these requirements when considering a revenue decision for the project. We will continue to engage with the proponents on changes affecting the project and the evidence supporting their view that the preferred option remains unchanged.