On 4 July 2025, we published our assessment of Ergon Energy's request to not reapply the regulatory investment test for distribution (RIT-D) in relation to a project to replace a static var compensator in its substation in Charleville, Queensland.
Following our assessment of Ergon Energy's request, we confirm that Ergon Energy is required to reapply the RIT-D for its Charleville project. We consider the reapplication of the RIT-D will provide an opportunity to identify the most efficient solution in the long-term interest of consumers.
Regulatory investment tests are a cost benefit analysis test which network businesses must apply before making major investment in their networks to address an identified need.