Review of Bulletin Board compliance following 10 August 2008 Moomba outage

Sector: 
Segment: 
Category: 
Compliance review
Release date: 
30 October 2008
Related provisions: 

Clause 172 of the National Gas Rules and clause 5.6(a) Bulletin Board procedures.

Event date: 
10 August 2008
Outcome: 

No further action

Overview

The AER has released its investigation report into the events of 10 August 2008, when there was a plant outage at the Moomba production facility. The production facility was not fully restored until Wednesday 13 August. In October 2008, the AER released its investigation report into the events of 10 August 2008, when there was a plant outage at the Moomba production facility. The production facility was not fully restored until Wednesday 13 August.

The AER has investigated compliance with Bulletin Board obligations following this outage.