On 1 July 2008, the AER approved EnergyAustralia’s contingent project application to replace the feeder cables 908 and 909, subject to an adjustment to the proposed capital expenditure allowance.

AER Decision - EnergyAustralia contingent project application - July 2008

Authors
AER
Content type
Document

CHC Consultant report to AER - Contingent project application by EnergyAustralia - June 2008