Overview

Application

On 28 March 2017, Powercor submitted an application to the AER seeking a determination, with respect to the installation of REFCLs and associated works, that funding for a contingent project be approved and their maximum allowed revenue be adjusted in accordance with clause 6.6A.2 of the NER.

Powercor - Contingent project application REFCL program (tranche one) - March 2017

Authors
Powercor Australia
Content type
Document

Supporting information

Powercor - REFCL.01 - Functional design scope (CND)

Authors
Powercor Australia
Content type
Document

Powercor - REFCL.02 - Functional design scope (CLC)

Authors
Powercor Australia
Content type
Document

Powercor - REFCL.03 - Functional design scope (CMN)

Authors
Powercor Australia
Content type
Document

Powercor - REFCL.04 - Functional design scope (MRO)

Authors
Powercor Australia
Content type
Document

Powercor - REFCL.05 - Functional design scope (WIN)

Authors
Powercor Australia
Content type
Document

Powercor - REFCL.06 - Functional design scope (EHK)

Authors
Powercor Australia
Content type
Document

Powercor - REFCL.07 - CLC zone substation options analysis

Authors
Powercor Australia
Content type
Document

Powercor - REFCL.08 - WIN zone substation options analysis

Authors
Powercor Australia
Content type
Document

Powercor - REFCL.09 - Implementation and optimisation of REFCL systems

Authors
Powercor Australia
Content type
Document

Powercor/AusNet Services - REFCL.10 - Powercor and AusNet Services Electricity Distribution Code compliance and REFCLs

Authors
AusNet Services
Powercor Australia
Content type
Document

ESCV - REFCL.11 - ESCV Re Electricity Distribution Code compliance and REFCLs

Authors
Essential Services Commission of Victoria (ESCV)
Content type
Document

REFCL.12 - Powercor Bushfire mitigation plan Revision 4.1

Authors
Powercor Australia
Content type
Document

GHD REFCL.13 - Review of Powercor surge arrester replacement strategy - March 2017

Authors
GHD
Content type
Document

Models

Powercor - REFCL_MOD.01 - Expenditure build-up mode (tranche one)

Authors
Powercor Australia
Content type
Document

Powercor - REFCL_MOD.02 - Amended PTRM

Authors
Powercor Australia
Content type
Document

Powercor - REFCL_MOD.03 - Amended depreciation model

Authors
Powercor Australia
Content type
Document

Powercor - REFCL_MOD.04 - Amended REPEX model

Authors
Powercor Australia
Content type
Document

Project administration

On 28 April 2017, the AER issued a notice to extend the deadline for making a decision in accordance with clause 6.6A.2(j) of the NER. The new date for the decision is on or before 21 August 2017.

Powercor - Contingent project extension of time - 28 April 2017 View details

Powercor - Contingent project extension of time - 28 April 2017.pdf
PDF (32.81KB)
Powercor - Contingent project extension of time - 28 April 2017.docx
DOCX (40.96KB)
Authors
AER
Content type
Document

Submissions

-

Submissions on Powercor's contingent project application closed on 8 May 2017.

Victorian Government - submission on contingent project applications - 8 May 2017

Authors
Environment and Climate Change (Victoria)
Content type
Document

Late submissions

During the course of the determination, the following submissions were received outside of the set consultation period.

Victorian Government - second submission on contingent project applications - 27 July 2017

Authors
Environment and Climate Change (Victoria)
Content type
Document

Powercor - submission on contingent project applications - 1 August 2017

Authors
Powercor Australia
Content type
Document

DELWP - submission on contingent project applications - 15 August 2017

Authors
Department of Environment, Land, Water & Planning (DELWP) - Victoria
Content type
Document

Victorian Government - third submission on contingent project applications - 17 August 2017

Authors
Environment and Climate Change (Victoria)
Content type
Document

AusNet - submission on contingent project applications - 18 August 2017

Authors
AusNet Services
Content type
Document

Powercor - second submission on contingent project applications - 18 August 2017

Authors
Powercor Australia
Content type
Document