Overview

Application

On 5 April 2022, Transgrid submitted its stage 1 contingent project application to the AER seeking an increase to their its revenue in accordance with clause 6A.8.2 of the NER to fund early works associated with the delivery of the staged HumeLink contingent project.

The HumeLink project is a transmission upgrade connecting the Snowy Mountains Hydroelectric Scheme to Bannaby. The HumeLink project is delivered across two stages: the early works stage comprised of pre-construction activities and the implementation stage. This project relates to the preferred network investment option identified through Transgrid’s HumeLink Regulatory Investment Test for Transmission (RIT-T).

The AER is required to make a determination on this contingent project application under clause 6A.8.2 of the NER.

A1 HumeLink Stage (Early Works) CPA Principal Application - 5 April 2022

Authors
Transgrid
Content type
Document

Supporting information

A2 HumeLink Scope definition - Stage 1 (early works) - 5 April 2022

Authors
Transgrid
Content type
Document

A3 Capex Forecasting Methodology - HumeLink Stage 1 (early works) - 5 April 2022

Authors
Transgrid
Content type
Document

A4 Labour and indirect costs - HumeLink Stage 1 Application - 5 April 2022

Authors
Transgrid
Content type
Document

A8 GHD - Independent Engineering Verification - Hume Link Stage 1 (Early Works) - 5 April 2022

Authors
GHD
Content type
Document

A1A HumeLink Stage 1 (early works) - 2018-23 PTRM

Authors
Transgrid
Content type
Document

A1B HumeLink Stage 1 (early works) - 2023-28 PTRM

Authors
Transgrid
Content type
Document

A1C HumeLink Stage 1 (early works) - 2018-23 RFM

Authors
Transgrid
Content type
Document

A1D HumeLink Stage 1 (early works) - 2018-23 Depreciation Model

Authors
Transgrid
Content type
Document

A5 HumeLink Stage 1 (early works) - Capex Forecast Model

Authors
Transgrid
Content type
Document

A6 HumeLink Stage 1 (early works) - Direct Non-Labour Model

Authors
Transgrid
Content type
Document

A7 HumeLink Stage 1 (early works) - Labour and Indirect Cost Model

Authors
Transgrid
Content type
Document

A7a HumeLink Stage 1 (early works) - Indirect Costs Artifacts 1

Authors
Transgrid
Content type
Document

A7b HumeLink Stage 1 (early works) - Indirect Costs Artifacts 2

Authors
Transgrid
Content type
Document

Confidentiality claims

Transgrid - Confidentiality claims - HumeLink Stage 1 (early works) CPA - 5 April 2022

Authors
Transgrid
Content type
Document

Submissions

-

We invited energy consumers and other interested parties to make submissions on Transgrid's contingent project application. The period for submissions has now closed.

EUAA - Humelink CPA submission - 30 May 22

Authors
Energy Users Association of Australia (EUAA)
Content type
Document

HumeLink Alliance - Humelink CPA submission - 30 May 2022

Authors
HumeLink Alliance
Content type
Document

Kyeamba Valley Concerned Landowners Group and Westwood Action Group - Humelink CPA submission - 30 May 2022

Authors
Various
Content type
Document

NPA - Humelink CPA submission - 30 May 2022

Authors
National Parks Association of NSW
Content type
Document

PIAC - Humelink CPA submission - 1 June 2022

Authors
Public Interest Advocacy Centre (PIAC)
Content type
Document

Pondera Pastoral Company - Humelink CPA submission - 30 May 2022

Authors
Pondera Pastoral Company
Content type
Document

Wunelli - Humelink CPA submission - 30 May 2022

Authors
Wunelli Pty Ltd (Wunelli)
Content type
Document

Braeburn Pastoral - Humelink CPA submission

Authors
Braeburn Pastoral
Content type
Document

Transgrid - EUAA HumeLink CPA Questions - 20 June 2022

Authors
Transgrid
Content type
Document

Individual Stakeholder 2 - Humelink CPA submission

Authors
Name withheld
Content type
Document

Project administration

The HumeLink project is delivered across two stages: the early works stage comprised of pre-construction activities and the implementation stage. This is to enable project uncertainty to be reduced and to identify project risks before committing to the full project.

The AER’s expectation in respect to the staging of the contingent project application process is set out in two letters between the AER and Transgrid, dated 14 September 2020 (from TransGrid) and 13 October 2020 (from the AER).

TransGrid letter to AER - HumeLink - Staging of the regulatory process - 14 September 2020

Authors
Transgrid
Content type
Document

AER letter to TransGrid - HumeLink - Staging of the regulatory process - 13 October 2020

Authors
AER
Content type
Document