On 15 September 2015, ElectraNet wrote to the AER requesting a determination on its 2014-15 network support pass through application. The AER assessed the application in accordance with clause 6A.7.2 of the NER.

On 9 November 2015, the AER approved the pass through amount without adjustment.

Key Documents

AER Decision - 2014-15 Network support pass through decisions for TransGrid and ElectraNet - 9 November 2015 View details

AER Decision - 2014-2015 Network support pass through decisions for TransGrid and ElectraNet - 9 November 2015.PDF
PDF (104.71KB)
AER Decision - 2014-2015 Network support pass through decisions for TransGrid and ElectraNet - 9 November 2015.DOCX
DOCX (214.61KB)
Authors
AER
Content type
Document