Overview

Decision

On 30 April 2026, the AER published its determination approving a positive pass through for Energex to recover incremental costs incurred due to Tropical Cyclone Alfred.

The AER’s decision is to approve a cost pass through amount of $66.1 million. This decision will allow Energex to recover these costs across the 2026-27 and 2027-28 regulatory years.

Details of the AER’s assessment against the relevant factors in the NER are set out in our decision document.

AER Determination - Energex - Tropical Cyclone Alfred cost pass through - April 2026