Overview

Decision#

On 20 September 2024, the AER published its determination on Jemena's cost pass through application to recover costs related to the Victorian Emergency Backstop Mechanism (VEBM).

Our decision is to approve a reduced positive pass through amount of $8.3 million (nominal, smoothed). Jemena will be able to recover this in the 2025–26 regulatory year. 

AER Determination - Jemena VEBM cost pass through - 20 September 2024

Authors
AER
Content type
Document

AER - Jemena electricity PTRM - 2024-25 Return on debt update (inc VEBM CPT) - September 2024

Authors
AER
Content type
Document