Overview

Sector
Electricity
Segment
Transmission
Region
South Australia
Status
Historical
Commencement date
Effective date

On 9 November 2021 Murraylink submitted its 2020–21 connection charge pass through application to the Australian Energy Regulator (AER) for determination. Murraylink’s pass through application is in relation to the difference between actual connection charges levied and the forecast connection charge amount for 2020–21 included in Murraylink’s 2018–23 revenue determination.

On 21 December 2021 the AER published its determination to approve a negative pass through amount of $836,582.

Key Documents

AER Determination - Murraylink 2020-21 connection charge cost pass through - December 2021