Overview

Sector
Electricity
Segment
Distribution
Region
South Australia
Status
Open
Commencement date
Effective date
AER reference
AER23006902

On 30 November 2023, SA Power Network submitted a cost pass through application to the AER, seeking to recover costs incurred responding to the flood event along the South Australian portion of the River Murray during the period November 2022 to February 2023. SA Power Networks is seeking an increase in allowed revenue of $11.10 million in 2024-25 to recover the incremental costs arising from the 2022-23 flood event. 

The AER will consider feedback received from stakeholders when making our determination on SA Power Networks’ application. We expect to make our determination in the first quarter of 2024. 

Key Documents