Overview

Application

-

On 28 February 2025, TasNetworks submitted a cost pass through application seeking to recover the costs it has incurred as a result of the August-September 2024 storm in Tasmania. TasNetworks is proposing an increased revenue allowance of $4.6 million ($nominal, smoothed) to be recovered over the final three years of the current regulatory period (2024-29) as follows: $1.2 million in 2026-27; $1.9 million in 2027-28; and $1.5 million in 2028–29.

TasNetworks - (D) - August-September 2024 storm cost pass through - Cover letter - 28 February 2025 - Public

Authors
TasNetworks (Distribution)
Content type
Document

TasNetworks - (D) - August-September 2024 storm cost pass through application - 28 February 2025 - Public

Authors
TasNetworks (Distribution)
Content type
Document

TasNetworks - (D) - Attachment 2 - August-September 2024 storm cost pass through - Distribution 2024-29 PTRM - 28 February 2025

Authors
TasNetworks (Distribution)
Content type
Document

Confidentiality Claims

TasNetworks - (D) - Attachment 3 - August-September storm cost pass through - Confidentiality template - 28 February 2025

Authors
TasNetworks (Distribution)
Content type
Document

Submissions

We invited energy consumers and other interested parties to make submissions on TasNetworks’ cost pass through application by 22 April 2025. We received the following submissions.

Carol-Ann Fletcher - Submission on TasNetworks August-September 2024 storm cost pass thorugh - 22 April 2025

Content type
Document

Lynette LaBlack - Submission on TasNetworks August-September 2024 storm cost pass thorugh - 22 April 2025

Content type
Document

Nekon Pty Ltd - Submission on TasNetworks August-September 2024 storm cost pass thorugh - 31 March 2025

Content type
Document

Rainforest Reserves Australia - Submission on TasNetworks August-September 2024 storm cost pass thorugh - 22 April 2025

Content type
Document