Overview

Sector
Electricity
Segment
Distribution
Region
New South Wales
Entities
Status
Current
Commencement date
Effective date

On 15 July 2022 Essential Energy submitted a waiver application under clause 5.2 of the Ring-fencing guideline (electricity distribution). Essential requested that the AER waive the obligations under clause 3.1 to allow it to lease excess capacity from its Sovereign Hills battery. The AER considered this waiver under its streamlined waiver process. 

On 4 August 2022 the AER granted a waiver for Essential Energy, with conditions. 

Key Documents

Essential Energy - Application - Ring-fencing waiver - 15 July 2022

Authors
Essential Energy
Content type
Document

AER - Final decision - Essential Energy - Ring-fencing waiver - August 2022

Authors
AER
Content type
Document