Project timeline

Overview

Engagements
Accepting submissions
Sector
Gas
Segment
Transmission
Region
Northern Territory
Status
Open
Commencement date
Effective date
Regulatory period
-

Access arrangement 2026-31

APT Pipelines (NT) Pty Ltd (APTNT) (an APA subsidiary) owns and operates the Amadeus Gas Pipeline in the Northern Territory. The National Gas Law (NGL) and National Gas Rules (NGR) provide the regulatory framework governing gas pipelines. As with other scheme pipelines, we regulate APTNT's reference tariffs - and through this its revenue - under an approved access arrangement.

On 14 January 2026, APTNT submitted a revised access arrangement for the Amadeus Gas Pipeline for the period 1 July 2026 to 30 June 2031. 

On 28 November 2025, we published our draft decision for the Amadeus Gas Pipeline 2026−31 access arrangement proposal. 

Interested stakeholders are invited to make a submission on both our draft decision and APTNT’s revised proposal. Submissions will close on Friday, 13 February 2026 and can be emailed to aergasresets2026-31ataer [dot] gov [dot] au (aergasresets2026-31[at]aer[dot]gov[dot]au).

An online public forum was scheduled for Monday 8 December 2025 for our 2026-31 gas access arrangement draft decisions on Evoenergy, AGN (SA) and Amadeus. 

Given limited stakeholder interest, this public forum did not proceed as originally indicated. 

We remain committed to engaging with stakeholders and encourage stakeholders who are interesting in discussing our draft decisions, or wish to provide feedback via alternative methods to reach out to Reset Coordination team on aergasresets2026-31ataer [dot] gov [dot] au (aergasresets2026-31[at]aer[dot]gov[dot]au)

Previous milestones - Amadeus Gas Pipeline's proposal

On 1 July 2025, we received a gas access arrangement proposal from Amadeus for its gas distribution network for the period 1 July 2026 to 30 June 2031. 

Stakeholder submissions on Amadeus's proposal closed on 15 August 2025 and are available on our website.

On 28 November 2025, we published our draft decision for the Amadeus Gas Pipeline 2026−31 access arrangement proposal. 

Key Documents

AGP - AAR 2026-31 - Access Arrangement (Clean) - June 2025

Authors
Amadeus Gas Pipeline
Content type
Document

AGP - AAR 2026-31 - Access Arrangement Overview - June 2025

Authors
Amadeus Gas Pipeline
Content type
Document

AGP - AAR 2026-31 - Access Arrangement (Tracked) - June 2025

Authors
Amadeus Gas Pipeline
Content type
Document

AER - Draft decision - Amadeus Gas Pipeline access arrangement 2026–31 - November 2025

Authors
AER
Content type
Document

AGP - Overview of the revised Access Arrangement - January 2026

Authors
APT Pipelines (NT) Pty Limited
Content type
Document