Overview

Indicative timetable

The AER received a reference service proposal from Multinet Gas Networks (Multinet) for the period 1 July 2028 to 30 June 2033. Under the NGL and the NGR, the AER has the function of reviewing and approving the terms of the proposal. Interested stakeholders are encouraged to consider the indicative dates for the key milestones in this review.

Indicative dates for key milestones in the decision making process
MilestoneDate*
Multinet reference service proposal due1 June 2026
AER publishes Multinet reference service final decision30 November 2026
Multinet submits access arrangement proposal1 June 2027
Stakeholder forum on Multinet's access arrangement proposalOptional
Stakeholder submissions on Multinet's access arrangement proposal closeJuly-August 2027*
AER publishes access arrangement draft decisionNovember 2027*
Multinet submits revised access arrangement proposalJanuary 2028*
Stakeholder submissions on Multinet's revised proposal and AER's draft decision closeFebruary 2028*
AER publishes access arrangement final decisionApril 2028*

* Please note this timeline is subject to change.

Reference service proposal

The AER received Multinet's reference service proposal on 1 June 2026.

Multinet Gas Networks 2028-33 - Reference Service Proposal - 1 June 2026

Authors
Multinet Gas
Content type
Document

Submissions

-

Interested parties are invited to make a submission on Multinet's reference service proposal to the AER via email to VICGAAR2028ataer [dot] gov [dot] au (VICGAAR2028[at]aer[dot]gov[dot]au) by 1 July 2026.