Overview

Indicative timetable

Indicative dates for key milestones in the decision making process
Milestone Date*
Submissions on proposal 3 September 2018
Draft determination 26 October 2018
Submissions on draft determination close 23 November 2018
Final determination 18 December 2018

*Please note this timeline is subject to change.

Application

On 7 June 2018, after lengthy pre-engagement, AGN submitted an application for a determination of future capital expenditure in relation to the Mount Barker gas network extension.

View documents

Submissions

-

Submissions on the proposed gas network extension to Mount Barker closed 3 September 2018.

View documents

Consultant reports

The AER commissioned a report from Zincara Pty Ltd on the robustness and overall reasonableness of the application.

Zincara consultant report on proposed gas network extension to Mount Barker - 2 October 2018