| Milestone | Date* |
|---|---|
| Consultation Paper published | 19 October 2018 |
| VCR Consultative Committee established | October 2018 |
| Submissions due on Consultation Paper | 16 November 2018 |
| VCR Consultative Committee meeting #1 | 28 November 2018 |
| Public forum - Sydney | 5 December 2018 |
| Public forum - Melbourne | 6 December 2018 |
| Presentation to Customer Consultative Group (CCG) | 11 December 2018 |
| Further stakeholder submissions in response to consultation paper and key issues raised at public forum and CCG | 20 December 2018 |
| All day workshop with MEI, KPMG/Insync on VCR methodology | 17 January 2019 |
| VCR Consultative Committee meeting #2 – VCR methodology and survey design | 7 February 2019 |
| VCR HILP sub-Committee meeting #1 – how to determine HILP VCR | 14 March 2019 |
| Publish Consultation update paper on methodology | 18 April 2019 |
| Commence Pilot | End April to 24 May 2019 |
| Submissions to Consultation update | 24 May 2019 |
| Insync report on pilot survey results | June 2019 |
| VCR Consultative Committee meeting #3 to discuss draft pilot survey results | 13 June 2019 |
| VCR Consultative Committee meeting #4 further discussion of pilot survey results | 25 July 2019 |
| VCR Consultative Committee meeting #5 discussion of draft decision methodology | 29 August 2019 |
| Conduct main survey and analyse results | September/October 2019 |
| Draft decision methodology | 18 September 2019 |
| Insync main survey draft report | End October 2019 |
| Submissions to draft decision | 18 October 2019 |
| Publish Final Decision Methodology (including HILP) | November 2019 |
*Please note this timeline is subject to change.