Ausgrid - Cost pass through - April 2015 storms

Sector: 
Segment: 
Status: 
Commencement date: 
21 August 2015
Effective date: 
1 July 2016
AER reference: 
58158

Overview

On 21 August 2015 Ausgrid applied to the AER for a positive cost pass through for restoration works conducted in response to the April 2015 storms.

On 3 December 2015 the AER determined that a positive pass through event has occurred and approved a positive pass through amount of $43.20 million ($' nominal) to be recovered from customers over three years, commencing 1 July 2016.