Ausgrid - Cost pass through - extension of time limit to submit 2016 application

Sector: 
Segment: 
Status: 
Commencement date: 
23 March 2016
Effective date: 
29 April 2016
Contact: 
AER General inquiries AERInquiry@aer.gov.au

Overview

On 23 March 2016, the AER received an application from Ausgrid requesting an extension of time to submit an application for the pass through of costs associated with the Expanding Competition in Metering and Related Services Rule Change. The AER received similar applications from Endeavour Energy on 31 March 2016, Essential Energy on 4 April 2016 and ActewAGL on 7 April 2016.

On 29 April 2016, the AER extended the time limit for Ausgrid to submit an application to pass through costs associated with the Expanding Competition in Metering and Related Services Rule Change to 90 business days after 1 December 2017. The same extension was also provided to Endeavour Energy, Essential Energy and ActewAGL.