Murraylink - Connection charge pass through 2020–21

Sector: 
Segment: 
Status: 
Commencement date: 
9 November 2021
Effective date: 
1 July 2022
Contact: 
AER General Inquiries AERInquiry@aer.gov.au

Overview

On 9 November 2021 Murraylink submitted its 2020–21 connection charge pass through application to the Australian Energy Regulator (AER) for determination. Murraylink’s pass through application is in relation to the difference between actual connection charges levied and the forecast connection charge amount for 2020–21 included in Murraylink’s 2018–23 revenue determination.

On 21 December 2021 the AER published its determination to approve a negative pass through amount of $836,582.