Sector:
Segment:
Status:
Commencement date:
16 September 2015
Effective date:
9 November 2015
Service provider/Asset:
Contact:
AER General Inquiries AERInquiry@aer.gov.au
AER reference:
58312
Overview
On 16 September 2015, TransGrid wrote to the AER requesting a determination on its 2014-15 network support pass through application. The AER assessed the application in accordance with clause 6A.7.2 of the NER.
On 9 November 2015, the AER approved the pass through amount without adjustment.