Energex - Determination 2020-25

Sector: 
Segment: 
Region: 
Commencement date: 
25 October 2017
Regulatory period: 
1 July 2020 to 30 June 2025 (5 years)
Status: 
Contact: 
General enquiries - Energy Queensland 2020 determinations EnergyQueensland2020@aer.gov.au

Overview

On 31 January 2019, Energex submitted its revenue proposal to the AER. The proposal sets out the revenue Energex proposes to collect from its customers through distribution charges from 1 July 2020 to 30 June 2025.

Delay to final decision

Following recent consultation with stakeholders, the Australian Energy Regulator (AER) has decided to delay its final 2020-25 network revenue determinations due on 30 April 2020. The AER now intends to release its final decision for Energex on 5 June 2020. Further information can be found on the "Updates" milestone here.

Draft decision

On 8 October 2019 we released our draft decision on Energex's regulatory proposal for the 2020-25 regulatory control period, commencing 1 July 2020. The draft decision represents a key milestone in our determination of the amount of revenue that Energex can recover from customers who use its network.

Energex now has the opportunity to consider our draft decision and submit its revised proposal and supporting material by 10 December 2019.

Invitation for submissions

We invite interested parties to make submissions on our draft decision and Energex's revised proposal by 15 January 2020.

Stakeholder forum

The AER hosted a public forum (pre-determination conference) on its draft decision for Energex on 24 October 2019.