28 October 2016
Regulatory period:
1 July 2019 to 30 June 2024 (5 years)
Status:
AER reference:
61051
Overview
On 30 April 2019, the AER published its final decision on the electricity determination for ACT distribution network service provider, Evoenergy, for the 2019-24 regulatory control period commencing 1 July 2019 to 30 June 2024.
On 29 November 2018, Evoenergy submitted its revised regulatory proposal for the 2019-24 period.
On 27 September 2018, the AER published its draft decision for Evoenergy for the 2019-24 period. On 5 December 2018, the AER also published its draft decision on Evoenergy's transmission pricing methodology in relation to Evoenergy's electricity distribution determination for the 2019-24 period.