Indicative timetable
Back to topIndicative dates for key milestones in the decision making process
Milestone | Date* |
---|---|
AER publishes F&A for Murraylink | 30 July 2021 |
Murraylink submits its regulatory proposal to AER | 31 January 2022 |
AER publishes an issues paper | 28 March 2022 |
Submissions on regulatory proposal close | 11 May 2022 |
AER publishes draft decision | 30 September 2022 |
AER holds a pre-determination conference | 12 October 2022 |
Murraylink submits revised regulatory proposal to AER | 2 December 2022 |
Submissions on revised regulatory proposal and draft decision close | 20 January 2023 |
AER publishes final decision | 28 April 2023 |
* Please note this timeline is subject to change.
Consultation
Back to topOn 30 November 2020 the AER released a notice on whether to amend or replace the current framework and approach (F&A) for Murraylink for the 2023–28 regulatory control period. This document outlines the purpose of the F&A and calls for submissions.
Documents (3) | Author |
---|---|
Murraylink - Request for revised framework and approach paper - 23 October 2020 ( PDF 87.52 KB ) | Murraylink |
AER - Murraylink 2023–28 - Notice calling for submissions to amend F&A - November 2020 ( PDF 183.73 KB ) | Murraylink |
AER - Murraylink framework and approach information sheet - November 2020 ( PDF 227.67 KB ) | Murraylink |
Submissions
Back to top30 November 2020 to 15 December 2020
Energy consumers and other interested parties were invited to make submissions on whether it is desirable to amend or replace the current F&A for Murraylink for the 2023–28 regulatory control period by 15 December 2020. We received no submissions.
Decision
Back to top30 December 2020
On 30 December 2020 the AER issued its decision to amend Murraylink's framework and approach.
Documents (1) | Author |
---|---|
AER - Murraylink framework and approach - Decision to amend - December 2020 ( PDF 456.39 KB ) | AER |