Sector:
Segment:
Region:
Service provider/Asset:
Commencement date:
3 April 2006
Regulatory period:
1 July 2007 to 30 June 2012 (5 years)
Status:
Overview
On 3 April 2006, Powerlink submitted a revenue cap application to the Australian Energy Regulator (AER) for the period 1 July 2007 to 30 June 2012. The AER is required to set a revenue cap for the non-contestable elements of the transmission services provided by Powerlink for the period.
On 14 June 2007, the AER released its final decision on the maximum allowed revenues that Powerlink is entitled to recover.
Key documents
Documents | Author |
---|---|
Final decision - Powerlink Queensland transmission network revenue cap - 14 June 2007 ( PDF 898.15 KB ) | AER |