Final decision
Back to topOn the 30 April 2012 the AER releasd its final decision on Powerlink's maximum allowable revenue for the regulatory control period 1 July 2012 to 30 June 2017.
Documents (2) | Author |
---|---|
Powerlink - Final decision - April 2012 ( PDF 3 MB ) | AER |
Powerlink - Transmission determination - April 2012 ( PDF 3.67 MB ) | AER |
Models
Back to topDocuments (2) | Author |
---|---|
Powerlink - Final decision RFM amended ( XLSM 1.45 MB ) | AER |
Powerlink - Final decision PTRM amended ( XLSM 1.65 MB ) | AER |
Consultant reports
Back to topThe AER commissioned a range of reports from consultants.
Documents (4) | Author |
---|---|
DAE Forecast growth in labour costs - 9 March 2012 ( PDF 1.36 MB ) | Deloitte Access Economics (DAE) |
DAE Response to issues raised in the Powerlink regulatory proposal - 2 March 2012 ( PDF 854.04 KB ) | Deloitte Access Economics (DAE) |
EMCa demand forecast review - 18 April 2012 ( PDF 957.41 KB ) | EMCa |
EMCa technical review - 18 April 2012 ( PDF 1.66 MB ) | EMCa |
Application
Back to topDocuments (1) | Author |
---|---|
Powerlink - Application to amend determination - Nominated pass through events - 30 October 2012 ( PDF 293.8 KB ) | Powerlink Queensland |
Submissions
Back to topOn 30 October 2012, Powerlink sought the AER's approval to include three nominated pass through events in its determination. Submissions closed 31 January 2013. No submissions were received.
Final decision
Back to topOn 8 March 2013, the AER made a decision to amend Powerlink's 2012-17 transmission determination to include certain pass through events.
Documents (1) | Author |
---|---|
Decision - Powerlink nominated cost pass through events - March 2013 ( DOCX 131.44 KB | PDF 247.59 KB ) | AER |