58158

On 21 August 2015 Ausgrid applied to the AER for a positive cost pass through for restoration works conducted in response to the April 2015 storms.

On 3 December 2015 the AER determined that a positive pass through event has occurred and approved a positive pass through amount of $43.20 million ($' nominal) to be recovered from customers over three years, commencing 1 July 2016.

Key Documents

AER - Determination - Ausgrid Pass Through Application for April 2015 Storms - December 2015 View details

AER - Determination - Ausgrid Pass Through Application for April 2015 Storms - December 2015.docx
DOCX (262.44KB)
AER - Determination - Ausgrid Pass Through Application for April 2015 Storms - December 2015.pdf
PDF (332.62KB)
Authors
AER
Content type
Document

AER - Determination - Ausgrid - Final decision and 2014-16 pass through - PTRM - Distribution - December 2015

Authors
AER
Content type
Document