On 3 December 2020, United Energy submitted its revised proposal for the 2021-26 regulatory control period.
Revised proposal
Models
In addition to the files below, United Energy has submitted MOD 4.07 - Pole condition model - December 2020. This spreadsheet file is too large to upload to our website and we can provide this file on request. Please email Vic2021-26
aer [dot] gov [dot] au (Vic2021-26[at]aer[dot]gov[dot]au) if you would like a copy of this file.
Supporting information
United Energy has claimed confidentiality of the following entire documents and fully redacted public versions were submitted. These documents have not been published:
- United Energy - Revised Regulatory Proposal - 2021-26 - ATT40 - Burwood Depot - December 2020
- United Energy - Revised Regulatory Proposal - 2021-26 - ATT46 - Insurance invoice 2018-19 - Oct2018 - December 2020
- United Energy - Revised Regulatory Proposal - 2021-26 - ATT47 - Insurance invoice 2019-20 - Nov2019 - December 2020
- United Energy - Revised Regulatory Proposal - 2021-26 - ATT48 - Insurance invoice 2020-21 - October 2020
- United Energy - Revised Regulatory Proposal - 2021-26 - ATT49 - Insurance invoice primary 2020-21 - December 2020
- United Energy - Revised Regulatory Proposal - 2021-26 - ATT53 - JMA Architects - Keysborough site concept plan - December 2020
- United Energy - Revised Regulatory Proposal - 2021-26 - ATT54 - JMA Architects - Keysborough office concept plan - December 2020
- United Energy - Revised Regulatory Proposal - 2021-26 - ATT51 - B2B - Burwood project and construction management budget estimate - December 2020
- United Energy - Revised Regulatory Proposal - 2021-26 - ATT55 - B2B - Keysborough project and construction management high level estimate - December 2020
Confidentiality claims - Confidentiality comparison template
United Energy - Revised regulatory proposal - APP11 - Confidentiality claim - December 2020
AER- Revised regulatory proposal - Table of Comparative Confidentiality Claims- December 2020
Update - Supplementary submissions
On 22 December 2020, CitiPower, Powercor and United Energy provided supplementary information for their revised proposal. The following documents and models have been provided.
United Energy - Revised Regulatory Proposal - 2021-26 - Supplementary revised proposal submission - December 2020
United Energy - Revised Regulatory Proposal - 2021-26 - MOD 9.03 - Category specific forecasts - December 2020
United Energy - Revised Regulatory Proposal - 2021-26 - MOD 10.02 - PTRM 2021-26 - 20201221 update - December 2020
United Energy - Revised Regulatory Proposal - 2021-26 - MOD 10.06 - Opex - 20201221 update - December 2020
Submissions
Submissions on our draft decision and United Energy's revised proposal closed 8 January 2021. The following submissions were received. We received a large number of submissions specific for Powercor and they are published with the Powercor submissions on its draft decision page.
Late submissions
Red Energy and Lumo Energy - Submission on the Victorian EDPR Revised Proposal and draft decision 2021-26 - 19 January 2021
Energy Consumers Australia - Submission and attachment on the Victorian EDPR Revised Proposal and Draft Decision 2021-26 - 20 January 2021
Update - Supplementary submissions
On 24 March 2021, United Energy provided supplementary information for their revised proposal. These updates relate to insurance premiums and Energy Safe Victoria levies. The following models have been provided: